Road bridge over Żerań Canal

InvestorGDDKiA Łódź
ScopeAssembly of the bridge
Mass121 Ton
LocationWarsaw, Poland
DateNovember 2011

PHOTOS from the assembly

Road bridge over Żerań Canal

Tarkon Sp. Zo.o. has taken on the task of performing welding work below the water level. In order to be able to do this, a special temporary structure was created in the production halls to allow underwater welding. When it was ready it was transported to Belgium, where on site employees of our company carried out welding work using the previously created structure.

Our company is also working on other projects both in Europe and abroad.